Redpath have delivered the refurbishment and fit out of the office space within the SPT Broomloan Depot to form a new training facility.

Works were carried out over a 3-week period during normal working hours, within the live operating environment of the SPT Subway Depot. Close co-ordination was required between SPT Facilities Management and the Redpath project team.

Works comprised the co-ordination of mechanical, electrical and air conditioning services. Formation of new acoustic rated partitions, including new fire rated door kits. The full finishes package included new flooring, suspended ceilings and decoration.

Key Facts / Information:

Client SPT
Value £50k
Duration 4 weeks
Lead Consultant Turner & Townsend
Sector/Type Office/Refurbishment/Fit out